
Project Information
Project Name: Bang Lang Dam Log Boom Rehabilitation
Location: Yala Province, Thailand
Owner: Electricity Generating Authority of Thailand
(EGAT)
Installation Year: 2025
Log Boom Locations: 2 Locations
Total Installed Length: 701 meters
Project Overview
TLEC Engineering was awarded the contract for the log boom rehabilitation works at Bang Lang Dam, operated by the Electricity Generating Authority of Thailand (EGAT).
The existing log boom system had deteriorated and required rehabilitation to restore operational efficiency and ensure continued debris control at the dam area. The scope of work included removal of existing components, relocation of the boom alignment, construction of a new reinforced concrete anchoring block, and reinstallation of the log boom lines in accordance with approved construction drawings.
A key technical consideration of this project was the installation and handling of a 556-meter steel sling system. Due to its substantial length and weight, the work required detailed lifting planning, precise load management, and coordinated installation procedures to maintain safety and system stability throughout the operation.
Scope of Work
-
Removal of existing log boom components
-
Relocation and alignment adjustment of log boom Line 1 (Total length: 556 meters)
-
Construction of reinforced concrete anchoring block (3.50 x 3.50 x 3.00 m)
-
Assembly and installation of log boom Line 1
-
Rehabilitation and installation of log boom Line 2 (Total length: 145 meters)
Power Intake
Replacement: November 2025
Length of Log Boom: 556 meters
No. of Span: 1














