Nam Theun 2 Hydropower

The Nam Theun 2 Hydropower Project (NT2) is a trans-basin diversion power plant on the Nam Theun river in Khammouane and Bolikhamsai provinces, Laos

Installed Capacity

1,070MW

Developer

Nam Theun 2 Power Company

Start of Construction

1999

Headrace Channel

Installation :  October 2017

Length of Log Boom : 220 meters

No. of Span : 1

DOWNSTREAM CHANNEL
Nam Gnom Siphon

Installation :  December 2017

Length of Log Boom : 80 meters

No. of Span : 1

Regulation Dam

Installation :  September 2018

Length of Log Boom : 482 meters

No. of Span : 1

Nakai Dam

Installation :  July2019

Length of Log Boom : 490 meters

No. of Span : 1