Project Overview
TLEC Engineering was appointed to carry out the installation of the log boom system at the Nam Che 1 Hydropower Project.
This project involved a new installation, including the supply and installation of a complete log boom system to regulate floating debris and enhance operational safety within the hydropower facility.
Scope of Work
-
Conduct site inspection and assessment prior to installation
-
Prepare engineering plan and define system configuration
-
Supply TLEC log boom system in accordance with project requirements
-
Carry out installation of the log boom system in compliance with technical standards
-
Supervise installation works and manage on-site safety control
Project Information
Project Name: Nam Che 1 Hydropower Project
Location: Xaisomboun Province, Lao PDR
Owner: B.Grimm Power Co., Ltd.
Installation Year: 2018
Log Boom Locations: 1 Locations
Total Installed Length: 200 meters